CHINA GROVE Crews will start digging out 75-year-old water pipes next week.It will mark the beginning of the end of water problems
that have plagued the town for decades.
Much of the main system was installed in 1925.
Clogged and broken pipes have been a neverending problem for the public works department.
Discolored and bad-tasting water has bothered residents.
Thursday afternoon, town officials met with
engineers and representatives of the general contractor. They went over the project that
will affect virtually every area of town and made a few changes.
The project will cost more than $2.4 million and
take just over a year to complete. Work crews will install many new lines and replace
thousands of feet of old lines.
R.F. Shinn Contractor Inc. of Concord is the
general contractor.
Where possible, crews will work on lines in
sidewalk areas, disrupting traffic as little as possible.
After the pre-construction meeting at the
Municipal Building, officials went to the Ketchie Street spot where digging is scheduled
to start.
Alderman Vernon Johnson briefly talked about the
project. Johnson, who led the effort to secure a state loan for the project, thanked board
members and others for their support on the project.
He pledged to continue efforts to get state grants
and loans to carry out a similar sewer project.
Board members agreed Thursday to some changes in
the work schedule.
Pipe replacement on Main Street will be done near
the end of the project. Johnson said one block will be done at a time to reduce
disruption.
If the 8-inch pipe needed for the Ketchie Street
section isnt immediately available, construction will start on N.C. 152 with
installation of 12-inch line.
Among a few glitches that surfaced Thursday is
difficulty in getting new fire hydrants. Johnson said the large number of water projects
under way has created a supply problem.
Public Works Director Kent Mishak said this week
that the new water lines will provide better water quality as well as more consistent
pressure throughout the town.
The improved pressure and flow is a key element in
the state fire insurance ratings, Mishak said. He added that the towns rating should
improve, reducing fire insurance premiums.
The hardware that will go in the ground includes:
- 33,000 feet of 12-inch line. Most will be on N.C.
152, Miller Road, Main Street, Thom Street, U.S. 29, Patterson Avenue and Elm Street.
- 7,500 feet of eight-inch line. It will be primarily
installed on a section of Ketchie Street and all of Franklin Street.
- 11,000 feet of six-inch line. It will be installed
in areas all over town, including Stokes Street, Grove Street, Haney Street, Third Avenue,
Eudy Road and other streets.
- In addition to other lines, crews will install 61
new hydrants and replace 425 service connections and 105 new valves.